15 Mar 2010:
"Construction Progress ending of February 2010"
Structural Work
- Tower Zone: Completed
- Internal Road: Completed
Architectural & Interior Work
- Room Unit: Completed with Reflection of Defect works
- Common area: Completed 95%
M&E Work
- L1 - L37: First Fixes completed
- L6 - L30: Second Fixes completed 98%
- Site Drainage: Completed 97%
Lift Work
- Service Lift: Completed for Operation
- Passenger Lift: Completed for Operation
|
|
|