Project Progress

15 Mar 2010:

"Construction Progress ending of February 2010"

Structural Work

  • Tower Zone: Completed
  • Internal Road: Completed
Architectural & Interior Work
  • Room Unit: Completed with Reflection of Defect works
  • Common area: Completed 95%
M&E Work
  • L1 - L37: First Fixes completed
  • L6 - L30: Second Fixes completed 98%
  • Site Drainage: Completed 97%
Lift Work
  • Service Lift: Completed for Operation
  • Passenger Lift: Completed for Operation