8 Aug 2008:
"Project Progress Update on August 2008"
For the construction stage, WIND Ratchayothin Residential Zone completed up
to L18 / Public Area rebar work of Swimming Pool Slab completed 10% / Underground Tanks
Removal of Earth Protection System completed 30%. For Architectural Work Residential Zone
Architectural Work L6 completed and Interior and Block Work is currently in progress for L7 –
L14. For M&E work Residential Zone L6 Completed 90% and 70% for L7 – L14