8 Aug 2008:
"Project Progress Update on August 2008"
For the construction stage, WIND Sukhumvit 23, Structure was constructed up to 20
th floor. Two lift core constructions are finished up to 21th and 24th floor. For Architectural
work, we commenced block work and plastering up to 13 th floor already. M&E work we
installed grounding; conduit, pipe work for toilet, pipe works for sprinkle, sleeve up to 12th
floor, swimming pool system etc. We expected that fully furnished and standard mock up
room will be finished in September 2008.