Project Progress

8 Aug 2008:

"Project Progress Update on August 2008"

For the construction stage, WIND Sukhumvit 23, Structure was constructed up to 20 th floor. Two lift core constructions are finished up to 21th and 24th floor. For Architectural work, we commenced block work and plastering up to 13 th floor already. M&E work we installed grounding; conduit, pipe work for toilet, pipe works for sprinkle, sleeve up to 12th floor, swimming pool system etc. We expected that fully furnished and standard mock up room will be finished in September 2008.